The Public Improvement Commission approved pedestrian easements and specific repairs for the Harvard Street Neighborhood Health Center project at Old Road, Ellington Street, and Michigan Avenue in Dorchester, including a raised intersection design. A joint petition by Verizon, Comcast, and Astound for telecommunications conduit installation at Mary Ellen McCormick development in South Boston was approved. The Eversource electric transformer vault petition at 16 Whitby Street, East Boston was continued to December 4 pending legal agreement finalization with the city.

Key Decisions (7)

Deferred

Eversource Electric Transformer Vault at 16 Whitby Street, East Boston

Petition by Enstar Electric Company DBA Eversource Energy for electric transformer vault installation within Whitby Street public way continued due to outstanding legal agreement between Eversource and the city. Eversource requested approval conditioned on not obtaining street opening permit until agreement signed, but chair preferred to wait for legal terms alignment.

Conditions: Continued pending finalization of legal agreement between Eversource and city
Approved

Pedestrian Easements at Ellington Street and Michigan Avenue, Dorchester

Harvard Street Support Corporation petition for acceptance of two pedestrian easements adjacent to Ellington Street (144 sq ft, 16 inches wide) and Michigan Avenue (142 sq ft, 22-24 inches wide) in Dorchester approved. Easements allow minimum five foot path of travel around building.

Vote: Unanimous (Aye)
Approved

Specific Repairs at Old Road, Ellington Street, Michigan Avenue, Dorchester

Harvard Street Support Corporation petition for specific repairs including curb realignment, sidewalk reconstruction, structural soil, pedestrian ramps, specialty pavement, street lighting, storm drain infrastructure, street trees, street furniture, bike racks, hydrants, driveway curb cuts, protected bicycle infrastructure, raised intersection, and 100-foot bus stop approved. MBTA approved updated bus stop design.

Vote: Unanimous (Aye)Conditions: Raised intersection incorporated with ramps on approach and departure
Approved

Canopy Projection License at 8 Old Road, Dorchester

Harvard Street Support Corporation petition for canopy projection over sidewalk at corner of Old Road and Ellington Street approved. Projection approximately 67 square feet, triangular shape with 9 inches projection on northern side and 34 inches on southern side, 33.5 feet wide along right of way.

Vote: Unanimous (Aye)
Approved

Telecommunications Conduit at Mary Ellen McCormick Development, South Boston

Joint petition by Verizon New England (lead), Comcast, and Astound (RCN) for grant of location to install new telecommunication conduit with city shadow within Major Michael J O'Connor Way and General Lawrence J Logan Way in South Boston approved. Second phase of Mary Ellen McCormick project development.

Vote: Unanimous (Aye)Conditions: Will replicate any handicap parking if needed
Approved

Pedestrian Easement at 15-17 Wichita Terrace, Dorchester

Petition by 1517 Wichita Terrace LLC for pedestrian easement extending sidewalk 3 feet outside proposed building to provide 5 feet total in front of building approved. Project obtained AAB variance.

Vote: Unanimous (Aye)
Approved

Specific Repairs at Wichita Terrace and River Street, Dorchester

Petition by 1517 Wichita Terrace LLC for curb realignment, roadway, sidewalk, and driveway curb cut reconstruction, pedestrian ramps, hydrants, and mountable curb approved. Work requested by Boston Fire Department to widen street from 16.5 feet to 20 feet for fire truck access. AAB variance granted for spot repair to existing sidewalks.

Vote: Unanimous (Aye)Conditions: AAB variance obtained for sidewalk width; note to be added to plans

Development Activity (6)

Harvard Street Neighborhood Health Center

Developer: Harvard Street Support Corporation / The Community BuildersLocation: Old Road, Ellington Street, Michigan Avenue, DorchesterType: CommercialStatus: Approved

New health center building with canopy projection, raised intersection, 100-foot bus stop, protected bicycle infrastructure, street trees, and pedestrian improvements

Mary Ellen McCormick Phase 2

Developer: Verizon New England (telecommunications infrastructure)Location: Major Michael J O'Connor Way and General Lawrence J Logan Way, South BostonType: InfrastructureStatus: Approved

Telecommunications conduit installation with city shadow, joint petition with Comcast and Astound

15-17 Wichita Terrace Residential

Developer: 1517 Wichita Terrace LLCLocation: 15-17 Wichita Terrace, DorchesterType: ResidentialStatus: Approved

New residential building requiring pedestrian easement and street improvements for fire access

635 Hyde Park Avenue Mixed-Use

Developer: 635 Hyde Park Ave LLCLocation: 635 Hyde Park Avenue at Canterbury Street, West Roxbury/RoslindaleType: Mixed-UseStatus: Under Review

Four story mixed use building with 27 dwelling units, 914 sq ft retail, 14 below-grade parking spaces, 9.5 foot sidewalks on Hyde Park Ave, 8 foot minimum on Canterbury Street, four street trees

700 Commonwealth Avenue Canopy

Developer: Trustees of Boston UniversityLocation: 700 Commonwealth Avenue, Boston (Charles River Campus)Type: CommercialStatus: Under Review

Removal of existing canopy and replacement with new canopy 11 feet 8 inches above sidewalk extending 8-10 feet, main entrance canopy 22 feet above sidewalk extending 15.5 feet

250 Everett Street Residential

Developer: MCRT Investments LLC / Mill Creek Residential TrustLocation: 250 Everett Street, BrightonType: ResidentialStatus: Under Review

Six story residential building with 240 units, subsurface garage for 110 vehicles, 8 foot cement concrete sidewalk, 4 foot furnishing zone, 10 new street trees, 27 foot curb cut, removal of 5 existing shade trees approved by parks department

Market Signals (4)

Housing Demand

Multiple residential developments advancing in Brighton and Dorchester including 240-unit project at 250 Everett Street and 27-unit mixed-use at 635 Hyde Park Avenue.

Infrastructure

Significant telecommunications and utility infrastructure investment ongoing at Mary Ellen McCormick development in South Boston with joint utility coordination between Verizon, Comcast, and Astound.

Infrastructure

National Grid replacing aging gas regulator stations installed in 1994 with new three-layer protection compliant equipment serving approximately 11,500 customers at Island Street/Gerard Street/Massachusetts Avenue intersection.

Infrastructure

MBTA and MassDOT bridge reconstruction on Canterbury Street causing significant regional traffic disruption; developers accommodating construction with lay down areas.