Skip to content
Fort Worth Meetings

CITY COUNCIL, August 25, 2026

Approved: Black Mountain Data Center PD 1420 amendment and site plan, passed

4h 25m35,563 words
124 mentionsmotion to approvepublic hearingzoningapprovedsetbackindustrialresidentialsubdivisioncommercialrezoningtabledrezonedeniedFort Worth, TX
Just researching this meeting? Get free Fort Worth alerts

What happened

On August 25, 2026, Fort Worth approved Black Mountain Data Center PD 1420 amendment and site plan.

Fort Worth City Council approved ZC 26-041, amending PD 1420 for the 187-acre Black Mountain data center campus on Lon Stevenson Road (adding an electrical substation use, raising maximum height from 55 to 70 feet, increasing the residential setback from 80 to 150 feet, amended o…

Meeting key facts
Jurisdiction
Fort Worth, TX
Governing body
Final authority
Date
August 25, 2026
Decisions
4 zoning decisions
Outcome
Approved, passed

Projects in this meeting (2)

5009-5033 Jacksboro Highway

Approved
5009-5033 Jacksboro Highway · Progress Land Development, LLC
1 condition of approval

Black Mountain Data Center PD 1420

Approved
4 conditions of approval
Open this project

Free sample: decision 1 of 4

Black Mountain Data Center PD 1420 amendment and site plan

The request amends PD 1420 on 187 acres along Lon Stevenson Road, adjacent to Anglin Drive and Forest Hill Drive. It adds an electrical substation use, raises the maximum building height from 55 to 70 feet, and increases the setback from single-family residential from 80 to 150 feet. Council Member Crane amended the motion on the floor to set the setback at 300 feet, consistent with the site plan. Parking is reduced to one space per four employees. The site plan shows four buildings with just over 1 million sq ft of ground footprint and over 2 million sq ft total, reduced from an earlier concept of 18 buildings and over 3 million sq ft. The prior zoning cases were ZC 24-153 and ZC 25-132. The developer and operator is EdgeConneX; Rhett Bennett of Black Mountain is the principal. The Zoning Commission unanimously approved the case on April 8. Many speakers asked the council to table the item pending the Data Center and Infrastructure Commission. The motion carried; speakers later indicated Council Members Flores and Martinez voted no.

  • setback amended to 300 feet
  • site plan tied to depicted dimensions
  • substation is a permitted use
  • drainage study and on-site detention required through platting

The other decisions are listed below. Available full write-ups and conditions are included with Pro.

Get every Fort Worth meeting with full decisions, votes, and zoning details, within hours of each session.

Fort Worth access in Pro, $39/month.

Key Decisions (4)

Approved

Black Mountain Data Center PD 1420 amendment and site plan

Vote: passed4 conditions attached
Approved

Zoning case ZC 26-097

Vote: passed
Approved

Public improvement district (PID) public hearings

Vote: passed
Approved

Atatiana Jefferson settlement

Vote: passedMoved by Chris Nettles

Full write-ups and conditions for all 4 decisions in Pro.

Zoning Changes (2)

1 additional zoning changes with full detail in Pro.

Development Activity (2)

Black Mountain Data Center Campus

Other

Project Ember

Other

Market Signals (3)

Infrastructure

Fort Worth has begun a data center moratorium process and…

Sentiment

Strong organized resident opposition to data centers signals political and…

Other

The city faces a FY2027 budget shortfall reported at $77M…

Who spoke

20 distinct speakers; 2 identified names.

All speaker roles: 8 Unknown, 1 Mayor, 8 Public, 2 Councilmember, 1 Clerk.

Identified name roles: 1 Mayor, 1 Councilmember.

Speaker sample: Mattie Parker, Mayor.

1 more identified name in Pro: 1 Councilmember.

Full speaker roster in Pro

Meeting audio

Listen to the recording and select a timestamp with Pro.

Audio in Pro

Zoning terms (13)

124 recorded timestamps

  • motion to approve (1 timestamps)
  • public hearing (5 timestamps)
  • zoning (48 timestamps)
  • approved (15 timestamps)
  • setback (17 timestamps)
  • industrial (8 timestamps)

Decision moments (4)

Ask this meeting anything

The transcript is ready. Ask questions with answers cited to this meeting in Pro.

Meeting Q&A in Pro

Questions you can ask

  • What conditions were attached to the decisions?
  • What were the recorded votes?
  • Who spoke, and what did they discuss?

Go deeper on this meeting

4 recorded decisions, 4 conditions across 1 decisions. Available full write-ups are included with Pro for Fort Worth.

Full write-up and conditions in Pro

Follow Fort Worth

Get the agenda when a meeting is posted, plus decision and analysis alerts.

We'll email you a 6-digit code, no password.

or