Assembly Committee of the Whole Worksession, May 4, 2026

Approved: Phase One HESCO barrier reinforcement to 63,500 CFS (Alternative 2), 7-2

3h 54m29,397 words
11 mentionsapprovedmotion to approveresidentialpublic hearingcommercialJuneau, AK
Just researching this meeting? Get free Juneau alerts

What happened

On May 4, 2026, Juneau approved Phase One HESCO barrier reinforcement to 63,500 CFS (Alternative 2) (7-2).

The Juneau Assembly Committee of the Whole voted 7-2 (Hall and Wall opposed) to authorize Alternative 2, reinforcing and raising CBJ's Phase One HESCO flood barriers and bank armoring along the Mendenhall River to protect against a 63,500 CFS glacial outburst flood (GLOF) before…

Meeting key facts
Jurisdiction
Juneau, AK
Date
May 4, 2026
Decisions
3 zoning decisions
Outcome
Approved, 7-2

Free sample: decision 1 of 3

Phase One HESCO barrier reinforcement to 63,500 CFS (Alternative 2)

Authorized Alternative 2 to reinforce and raise CBJ Phase One HESCO barriers and associated bank armoring along the Mendenhall River for the 2026 GLOF, protecting against a 63,500 CFS event. The plan leaves a roughly $3M shortfall beyond the $11.8M available; Option 3 (90,000 CFS, $19.8M) would leave an $8M shortfall. An appropriating ordinance is to be introduced May 18. Roll call passed 7-2, with Hall and Wall voting no. This was the manager's recommendation.

The other decisions are listed below. Available full write-ups and conditions are included with Pro.

Get every Juneau meeting with full decisions, votes, and zoning details, within hours of each session.

Juneau access in Pro, $39/month.

Key Decisions (3)

Approved

Phase One HESCO barrier reinforcement to 63,500 CFS (Alternative 2)

Vote: 7-2Moved by Weldon
Approved

Forward Goldbelt RSA repayment ordinances to public hearing

Vote: 8-1Moved by Weldon
Approved

Terminate Eaglecrest Pulse Gondola project (Option A)

Vote: unanimousMoved by Hughes-Scandies

Full write-ups and conditions for all 3 decisions in Pro.

Development Activity (2)

Mendenhall River Phase Two HESCO barriers (USACE)

Infrastructure

Eaglecrest Pulse Gondola

Other

Market Signals (3)

Infrastructure

A 90,000 CFS GLOF could impact over 2,000 residential properties…

Labor

Local contractor labor is heavily absorbed by the flood-barrier work…

Other

Officials are weighing replacing the Phase One LID with a…

Who spoke

17 distinct speakers; 16 identified names.

All speaker roles: 3 Witness, 5 Staff, 6 Councilmember, 1 Chair, 1 Clerk, 1 Mayor.

Identified name roles: 3 Witness, 6 Councilmember, 1 Chair, 4 Staff, 1 Clerk, 1 Mayor.

Speaker sample: Smith, Chair.

15 more identified names in Pro: 3 Witness, 6 Councilmember, 4 Staff, 1 Clerk, 1 Mayor.

Full speaker roster in Pro

Meeting audio

Listen to the recording and select a timestamp with Pro.

Audio in Pro

Zoning terms (5)

11 recorded timestamps

  • approved (5 timestamps)
  • motion to approve (1 timestamps)
  • residential (1 timestamps)
  • public hearing (3 timestamps)
  • commercial (1 timestamps)

Decision moments (3)

Ask this meeting anything

The transcript is ready. Ask questions with answers cited to this meeting in Pro.

Meeting Q&A in Pro

Questions you can ask

  • What were the recorded votes?
  • Who spoke, and what did they discuss?

Go deeper on this meeting

3 recorded decisions. Available full write-ups are included with Pro for Juneau.

Full write-up and conditions in Pro

Follow Juneau

Get the agenda when a meeting is posted, plus decision and analysis alerts.

We'll email you a 6-digit code, no password.

or