Board of County Supervisors Meeting - Work Session, June 9, 2026

Approved: Data Center Overlay ZTA Initiation (DCOZOD), unanimous

3h 51m32,944 words
44 mentionszoningland usecomprehensive plancommercialvarianceapprovedhistoric preservationresidentialoverlay districtspecial use permitpublic hearingindustrialPrince William County, VA
Just researching this meeting? Get free Prince William County alerts

What happened

On June 9, 2026, Prince William County approved Data Center Overlay ZTA Initiation (DCOZOD) (unanimous).

This was a work session of the Prince William County Board of County Supervisors focused primarily on strategic plan updates, public health briefings, and a 3-1-1 system update; no development entitlements were decided at the meeting itself.

Meeting key facts
Jurisdiction
Prince William County, VA
Governing body
Final authority
Date
June 9, 2026
Decisions
7 zoning decisions
Outcome
Approved, unanimous

Projects in this meeting (3)

Data Center Overlay ZTA Initiation

Approved
3 conditions of approval

Directive

Awaiting final vote
3 conditions of approval

Board-Initiated

Approved 5-2
11480, 11500, 11520, 11530, and 11540 Nokesville Road
3 conditions of approval
Open this projectProject Report, $19 · or in Pro

Free sample: decision 1 of 7

Data Center Overlay ZTA Initiation (DCOZOD)

Board adopted a resolution initiating a new zoning text amendment to the Data Center Opportunity Zone Overlay District (county code section 32-509.01), to amend data center uses permitted by right and by special use permit, including corresponding DCOZOD map amendments. Rescinds the prior initiation adopted by Resolution 26-125 on March 3, 2026 (which had been halted by Directive 26-11 on May 19, 2026). Reflects edits recommended by advisory boards and planning staff.

  • county staff directed to give highest priority to the ZTA
  • target bringing final ZTA back for public hearing in September 2026
  • rescinds initiation of ZTA adopted by Resolution 26-125

The other decisions are listed below. Available full write-ups and conditions are included with Pro.

Prince William County access in Pro, $39/month.

Key Decisions (7)

Approved

Data Center Overlay ZTA Initiation (DCOZOD)

Vote: unanimous3 conditions attachedMoved by Tom Gordy
Approved

Board-Initiated Rezoning at Nokesville Road (approx. 55.31 acres)

Vote: 5-23 conditions attachedMoved by Tom Gordy
Other

Directive on HB 153 / SB 94 high energy user site assessments

Other

Directive to explore ORPA zoning district (Occoquan Reservoir Protection Area)

3 conditions attachedMoved by Vega
Other

Directive on solar parking canopy provisions (HB 1234 / SB 36)

3 conditions attachedMoved by Kenny Bodie
Other

Directive on Veterans Memorial Park pickleball/basketball court lighting and camera

3 conditions attachedMoved by Jeannie LaCroix
Other

Directive amending Directive 26-12 re Dominion transmission line routing

Full write-ups and conditions for all 7 decisions in Pro.

Zoning Changes (1)

A-1PBDapproximately 55.31 acres

Market Signals (5)

Commercial Demand

The county is running out of land in Innovation Park…

Infrastructure

Data center power demand is escalating (from ~30 MW to…

Sentiment

Strong and organized public opposition to data centers persists in…

2 additional market signals with full detail in Pro.

Who spoke

20 distinct speakers; 19 identified names.

All speaker roles: 13 Staff, 6 Commissioner, 1 Chair.

Identified name roles: 12 Staff, 6 Commissioner, 1 Chair.

Speaker sample: Kimberly Sparks, Staff.

18 more identified names in Pro: 11 Staff, 6 Commissioner, 1 Chair.

Full speaker roster in Pro

Meeting audio

Listen to the recording and select a timestamp with Pro.

Audio in Pro

Zoning terms (12)

44 recorded timestamps

  • zoning (17 timestamps)
  • land use (6 timestamps)
  • comprehensive plan (4 timestamps)
  • commercial (3 timestamps)
  • variance (1 timestamps)
  • approved (2 timestamps)

Decision moments (7)

Ask this meeting anything

The transcript is ready. Ask questions with answers cited to this meeting in Pro.

Meeting Q&A in Pro

Questions you can ask

  • What conditions were attached to the decisions?
  • What were the recorded votes?
  • Who spoke, and what did they discuss?

Go deeper on this meeting

7 recorded decisions, 15 conditions across 5 decisions. Available full write-ups are included with Pro for Prince William County.

Full write-up and conditions in Pro

Follow Prince William County

Get the agenda when a meeting is posted, plus decision and analysis alerts.

We'll email you a 6-digit code, no password.

or