Board of Supervisors, September 15, 2026
Approved: Foundation Component GPA 240062 initiation, R.J. Noble asphalt plant, Temescal Canyon, passed
What happened
On September 15, 2026, Riverside County approved Foundation Component GPA 240062 initiation, R.J. Noble asphalt plant, Temescal Canyon.
Riverside County Board of Supervisors denied initiation of Foundation Component General Plan Amendment GPA 240053 (22 parcels, roughly 379-410 acres in the Sage area south of East Benton Road), which would have changed Rural Residential (5-acre minimum) to Rural Community Very Lo…
- Jurisdiction
- Riverside County, CA
- Governing body
- Final authority
- Date
- September 15, 2026
- Decisions
- 9 zoning decisions
- Outcome
- Approved, passed
Projects in this meeting (1)
A project bundles every related decision, across hearingsFoundation Component GPA 240077 initiation, Gavilan Hills
Awaiting final voteFree sample: decision 1 of 9
Foundation Component GPA 240053 initiation in Sage
The request would have changed the foundation component of 22 parcels from Rural Residential (5-acre minimum) to Rural Community Very Low Density Residential (1-2 acre lots). The site is south of East Benton Road, north of Calle Cordova, east of De Portola Road, and west of Sage Road in the 3rd District, Southwest Area Plan. The applicant had originally proposed community development medium/high density and mixed use. The Planning Commission was split: 1 support, 2 against, 1 neutral. 17 public speakers testified, overwhelmingly opposed, citing water, sewer, fire evacuation, and traffic. The applicant was referred to as Dr. Chaudhry. Supervisor Washington moved to deny; the Board denied initiation 5-0. The applicant must wait for the next 8-year cycle.
The other decisions are listed below. Available full write-ups and conditions are included with Pro.
Get every Riverside County meeting with full decisions, votes, and zoning details, within hours of each session.
Riverside County access in Pro, $39/month.
Key Decisions (9)
Foundation Component GPA 240053 initiation in Sage
Foundation Component GPA 240062 initiation, R.J. Noble asphalt plant, Temescal Canyon
Foundation Component GPA 240077 initiation, Gavilan Hills
Rangel Steel fabrication facility, Thousand Palms
RIVCO Clean illegal dumping initiative
Teeter Plan financing
Response to civil grand jury report on jail deaths
UCR veterinary school feasibility study
Public guardian report
Full write-ups and conditions for all 9 decisions in Pro.
Zoning Changes (1)
Development Activity (4)
R.J. Noble asphalt plant, Temescal Canyon
Industrial
24-lot residential subdivision, Gavilan Hills
Residential
Sage rural residential project
Residential
Rangel Steel fabrication facility
Industrial
Market Signals (4)
Housing Demand
Riverside County supervisors rejected upzoning rural Sage land from 5-acre…
Infrastructure
The nearest EMWD sewer line is 3.5 miles from the…
Commercial Demand
A prospective data center on state-owned Perris fairgrounds land was…
Commercial Demand
Industrial entitlements in Thousand Palms and Temescal Canyon advanced, while…
Agenda results
Each land-use item on the agenda, with its recorded voteSan Jacinto Rd subdivision
2 CONSENT CALENDAR - 2.1 31379 SUPERVISOR JOSE MEDINA: Receive and File the RivCo Clean… subdivision
3240 Hamner Avenue rezone
14 FLOOD CONTROL AND WATER CONSERVATION DISTRICT MEETING - 14.1 31100 FLOOD CONTROL… request
Alfredo Rangel – Engineer rezone
Who spoke
20 distinct speakers; 5 identified names.
All speaker roles: 6 Public, 4 Councilmember, 1 Clerk, 1 Staff, 7 Unknown, 1 Chair.
Identified name roles: 4 Councilmember, 1 Chair.
5 more identified names in Pro: 4 Councilmember, 1 Chair.
Full speaker roster in Pro
Meeting audio
Listen to the recording and select a timestamp with Pro.
Audio in Pro
Zoning terms (15)
129 recorded timestamps
- land use (13 timestamps)
- industrial (16 timestamps)
- public hearing (8 timestamps)
- environmental review (2 timestamps)
- approved (12 timestamps)
- traffic study (1 timestamps)
Decision moments (9)
Ask this meeting anything
The transcript is ready. Ask questions with answers cited to this meeting in Pro.
Meeting Q&A in Pro
Questions you can ask
- What conditions were attached to the decisions?
- What were the recorded votes?
- Who spoke, and what did they discuss?
Go deeper on this meeting
9 recorded decisions, 3 conditions across 3 decisions. Available full write-ups are included with Pro for Riverside County.
Full write-up and conditions in Pro
Follow Riverside County
Get the agenda when a meeting is posted, plus decision and analysis alerts.
We'll email you a 6-digit code, no password.