Public Infrastructure and Conservation Committee, April 7, 2026

Recommends approval: 2026-2028 Facilities On-Call Consultant Services Master Agreements

11m1,709 words
1 mentionapprovedSnohomish County, WA
Just researching this meeting? Get free Snohomish County alerts

What happened

On April 7, 2026, the Public Infrastructure and Conservation Committee recommended approval of 2026-2028 Facilities On-Call Consultant Services Master Agreements.

The Snohomish County Council Public Infrastructure and Conservation Committee approved seven motions for consent consideration, primarily involving change orders for the Arlington Operations Center progressive design-build project totaling approximately $228,472 and various infra…

Meeting key facts
Jurisdiction
Snohomish County, WA
Governing body
Advisory (makes a recommendation)
Date
April 7, 2026
Decisions
7 zoning decisions
Outcome
Recommends approval
Next step
Final board vote (pending)

Free sample: decision 1 of 7

Change Order #3 for Arlington Operations Center - Rock Fill

Approved change order for additional rock fill needed for hoop buildings interior floor drains to meet 1% slope drainage requirements. Amount: $41,960.01. Contractor: Cornerstone General Contractors under Progressive Design-Build Agreement PDB01-23.

The other decisions are listed below. Available full write-ups and conditions are included with Pro.

Get every Snohomish County meeting with full decisions, votes, and zoning details, within hours of each session.

Snohomish County access in Pro, $39/month.

Key Decisions (7)

Recommends Approval

Change Order #3 for Arlington Operations Center - Rock Fill

Recommends Approval

Change Order #4 for Arlington Operations Center - AV Equipment

Recommends Approval

Change Order #5 for Arlington Operations Center - Jersey Barriers

Recommends Approval

Traffic Data Collection Equipment Contract

Recommends Approval

Wave Broadband Cable Franchise Extension

Recommends Approval

2026-2028 Facilities On-Call Consultant Services Master Agreements

1 conditions attached
Recommends Approval

Denny Juvenile Justice Center Roof Repairs Change Order #2

1 conditions attached

Full write-ups and conditions for all 7 decisions in Pro.

Development Activity (1)

Arlington Operations Center

Infrastructure

Market Signals (3)

Infrastructure

Snohomish County is investing over $30.9 million in a new…

Infrastructure

County is modernizing traffic data collection systems with new equipment…

Other

County's progressive design-build process for the Arlington Operations Center is…

Meeting audio

Listen to the recording and select a timestamp with Pro.

Audio in Pro

Zoning terms (1)

1 recorded timestamp

  • approved (1 timestamps)

Decision moments (7)

Ask this meeting anything

The transcript is ready. Ask questions with answers cited to this meeting in Pro.

Meeting Q&A in Pro

Questions you can ask

  • What conditions were attached to the decisions?

Go deeper on this meeting

7 recorded decisions, 2 conditions across 2 decisions. Available full write-ups are included with Pro for Snohomish County.

Full write-up and conditions in Pro

Follow Snohomish County