Meeting Summary

The Board of Legislators approved prevailing wage requirements for county lease construction projects (Act 2026-118), authorized $43.1M in appropriations transfers to close fiscal year 2025, and approved $3.54M for chiller replacement at Norwood E. Jackson Correctional Center. Public hearings were set for County Water District pumping station improvements and a 15-year Citigroup hangar lease at Westchester County Airport.

Key Decisions (10)

Approved

Prevailing Wage Requirements for County Lease Construction

Act requiring lessors of county lease property to use contractors paying prevailing wage for construction projects over $250,000 on leases of 10 years or longer where there is public benefit. Closes gap where county-related construction may fall outside prevailing wage requirements.

Vote: 17-0 unanimousConditions: Applies to leases 10 years or longer, construction over $250,000, and where public benefit exists
Approved

FY2025 Appropriations Transfer

Act authorizing transfer of $43,104,337 in appropriations across county departments to close out 2025 fiscal year. Routine year-end action that does not increase overall spending.

Vote: 17-0 unanimous
Approved

2025 County Operating Budget Amendment

Act authorizing amendment to 2025 county operating budget in the amount of $27,744,180.

Vote: 17-0 unanimous
Approved

Propel New York Energy Transmission Project Easements

Act authorizing permanent and temporary easements to New York Power Authority and New York Transco LLC over county roads and property in Yonkers, Tuckahoe, Eastchester, and Bronx River Parkway reservation for underground electric transmission lines.

Vote: 17-0 unanimous
Approved

Edward Byrne Memorial Justice Assistance Grant

Act accepting $75,504 federal grant from DOJ Bureau of Justice Assistance with inter-municipal agreements. Yonkers receives approximately $36,000 for police overtime, Mount Vernon receives approximately $21,000 for body camera technology, county receives funding for narcotics and violent crime investigations.

Vote: 17-0 unanimous
Approved

Correctional Facility Chiller Replacement Capital Budget Amendment

Act amending 2026 capital budget appropriations of $3,540,000 for Capital Project BCR66 to replace failed chiller system at Norwood E. Jackson Correctional Center. Chiller CH3 failed at 26 years old; temporary chiller to be installed for summer while new energy-efficient chiller with variable frequency drive is installed.

Vote: 17-0 unanimousConditions: Temporary chiller to be installed for summer 2026 while permanent replacement is tested for next year
Approved

Correctional Facility Chiller Replacement Bond Act

Bond act authorizing issuance of $3,540,000 in bonds to finance Capital Project BCR66, Correctional Facility Chiller Replacement.

Vote: 17-0 unanimous
Other

Public Hearing Set - County Water District Eastview Pumping Station

Resolution setting public hearing for May 18, 2026 at 7:30 PM on authorizing Capital Project WD305, County Water District Number 1 Eastview Pumping Station for benefit of County Water District Number 3.

Vote: 17-0 unanimous
Other

Public Hearing Set - Citigroup Hangar Lease at Westchester County Airport

Resolution setting public hearing for May 18, 2026 at 7:30 PM on lease agreement with Citigroup Inc. for Hangar E, Bay 2 and related space at Westchester County Airport for initial 15-year term with two 5-year option terms.

Vote: 17-0 unanimous
Deferred

Item 2026-176 Postponed

Item postponed to June 1, 2026 regular meeting at 7 PM to allow community advocates and stakeholders opportunity to weigh in.

Conditions: Postponed to June 1, 2026

Development Activity (2)

Propel New York Energy Underground Electric Transmission Project

Developer: New York Power Authority and New York Transco LLCLocation: Yonkers, Tuckahoe, Eastchester, and Bronx River Parkway reservation areaType: InfrastructureStatus: Approved

Underground electric transmission lines and related infrastructure across multiple portions of the county

Citigroup Hangar Lease - Westchester County Airport

Developer: Citigroup Inc.Location: Hangar E, Bay 2, Westchester County AirportType: CommercialStatus: Under Review

Lease agreement for hangar and related space with initial 15-year term and two 5-year option terms

Market Signals (3)

Infrastructure

County investing in energy infrastructure with Propel New York underground transmission project spanning multiple municipalities including Yonkers, Tuckahoe, and Eastchester.

Commercial Demand

Citigroup seeking 15-year lease with extension options at Westchester County Airport indicates corporate aviation demand.

Labor