Project · 1 decision so far · Chesterfield County, VA · Updated today
ATB LLC / Servpro 100-foot buffer landscape plan
Tracking this deal? Follow it free, we'll email you when there's a decision
Sourced from Chesterfield County meeting, Mar 17, 2026. ZoneWire tracks 108 projects in Chesterfield County, VA, updated within 24h of every meeting.
Where this stands
ATB LLC / Servpro 100-foot buffer landscape plan at Cloverhill Industrial Park
- Planning Commission recommended approval unanimously on Mar 17, 2026.
- Project
- ATB LLC / Servpro 100-foot buffer landscape plan
- Developer
- ATB LLC
- County
- Chesterfield County, VA
- Jurisdiction
- Chesterfield County
- Latest action
- ATB LLC / Servpro 100-foot buffer landscape plan at Cloverhill Industrial Park
- Current status
- Awaiting final vote
The hearing chain
how this case has moved, and where it goes next- Mar 17, 2026 · Planning Commission · Recommended
- Final vote pending · pending
3 conditions of approval
Sample condition, 1 of 3: 100-foot buffer maintained adjacent to residential zoning
The other 2 conditions of approval, verbatim, plus the amendments that changed the deal, are in the Project Report.
1 credit ($19), or Pro at $39/mo with 3 Project Reports included
The whole board record on this parcel, in one report.
Everything on this project, assembled: the decision in full through the pending vote, every condition, and the source links. One project, one price.
- Where it stands today, with the source meeting linked
- This hearing in full, plus we track the pending vote
- All 3 conditions of approval, verbatim
- The applicant's filings and representative
1 credit ($19), or Pro at $39/mo with 3 Project Reports included
1 hearing, the 3 conditions verbatim, and the vote where one was recorded. More decisions attach to this project as they are heard, at no extra cost.
A manual parcel zoning report from Gridics starts at $999. This is not that report and does not replace it: it is the board record on this parcel, for $19.
Follow this project, free
We'll email you the staff recommendation, the vote, and every condition the morning after each hearing, starting with the next pending vote. No card.
We'll email you a 6-digit code, no password.
Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.
Learn about Meeting Q&AMore projects in Chesterfield County
- Walton Station · Continued
- Cottage Glen Phase 3 · Approved
- Watts Accessory Dwelling Unit · Approved
- Whitby East Genito Road Residential · Continued
- Munster Battery Energy Storage Facility · Approved