Project · 1 decision so far · Coweta County, GA · Updated today
Go Church campus expansion, East Highway 34 & Lassiter Road
Tracking this deal? Follow it free, we'll email you when there's a decision
Sourced from Coweta County meeting, Jul 23, 2026. ZoneWire tracks 49 projects in Coweta County, GA, updated within 24h of every meeting.
Where this stands
Conditional use permit for Go Church campus expansion, East Highway 34 & Lassiter Road
- Project
- Go Church campus expansion, East Highway 34 & Lassiter Road
- Asset class
- Institutional
- County
- Coweta County, GA
- Jurisdiction
- Coweta County
- Latest action
- Conditional use permit for Go Church campus expansion, East Highway 34 & Lassiter Road
- Current status
- Voted
The hearing chain
how this case has moved, and where it goes next4 conditions of approval
Sample condition, 1 of 4: Future expansion of the main assembly area greater than 25% of 23,266 square feet requires a new conditional use application
The other 3 conditions of approval, verbatim, plus the amendments that changed the deal, are in the Project Report.
Follow this project, free
We'll email you the staff recommendation, the vote, and every condition the morning after each hearing. No card.
We'll email you a 6-digit code, no password.
Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.
Learn about Meeting Q&AMore projects in Coweta County
- Roadways and open space deed, Chapel Hill Phase 4A · Approved
- Zoning reversion of Project Peach data center site to RC · Approved
- 1585 Tommy Lee Cook Road · Denied
- 3 Normal Lane · Approved
- Front Setback Reduction · Voted