Project · 1 decision so far · Hanover County, VA · Updated today
Iron Horse Data Center
Tracking this deal? Follow it free, we'll email you when there's a decision
Sourced from Hanover County meeting, Aug 20, 2026. ZoneWire tracks 84 projects in Hanover County, VA, updated within 24h of every meeting.
Where this stands
Iron Horse Data Center Rezoning at East Patrick Henry Road (Tradeport Hanover Land, LLC)
- Planning Commission Meeting recommended approval 4-3 on Aug 20, 2026.
- Project
- Iron Horse Data Center
- Asset class
- Data Center
- Developer
- West Dulles Properties
- County
- Hanover County, VA
- Jurisdiction
- Hanover County
- Latest action
- Iron Horse Data Center Rezoning at East Patrick Henry Road (Tradeport Hanover Land, LLC)
- Current status
- Awaiting final vote
The hearing chain
how this case has moved, and where it goes next- Aug 20, 2026 · Planning Commission Meeting · Recommended
- Final vote pending · pending
3 conditions of approval
Sample condition, 1 of 3: Amend Proffer 9(B) so private wells are prohibited (strike 'for cooling')
The other 2 conditions of approval, verbatim, plus the amendments that changed the deal, are in the Project Report.
1 credit ($19), or Pro at $39/mo with 3 Project Reports included
The whole board record on this parcel, in one report.
Everything on this project, assembled: the decision in full through the pending vote, every condition, and the source links. One project, one price.
- Where it stands today, with the source meeting linked
- This hearing in full, plus we track the pending vote
- All 3 conditions of approval, verbatim
- The applicant's filings and representative
1 credit ($19), or Pro at $39/mo with 3 Project Reports included
1 hearing, the 3 conditions verbatim, and the vote where one was recorded. More decisions attach to this project as they are heard, at no extra cost.
A manual parcel zoning report from Gridics starts at $999. This is not that report and does not replace it: it is the board record on this parcel, for $19.
Follow this project, free
We'll email you the staff recommendation, the vote, and every condition the morning after each hearing, starting with the next pending vote. No card.
We'll email you a 6-digit code, no password.
Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.
Learn about Meeting Q&AMore projects in Hanover County
- Normansbridge Road, Beaver Dam District · Awaiting final vote
- Mill Run, Inc. rezoning · Awaiting final vote
- Elmont Road · Awaiting final vote
- 2026-00017 Nash Lane · Awaiting final vote
- Ordinance 2610 · Awaiting final vote