Project · 2 decisions so far · Hanover County, VA · Updated today
Substations - Valco Hanover County 4
Tracking this deal? Follow it free, we'll email you when there's a decision
Sourced from Hanover County meeting, Apr 16, 2026. ZoneWire tracks 77 projects in Hanover County, VA, updated within 24h of every meeting.
Where this stands
Conditional Use Permit for substations - Valco Hanover County 4
- Board of Supervisors Meeting denied it 4-3 on May 27, 2026.
- Project
- Substations - Valco Hanover County 4
- Asset class
- Data Center
- County
- Hanover County, VA
- Jurisdiction
- Hanover County
- Latest action
- Conditional Use Permit for substations - Valco Hanover County 4
- Current status
- Denied
The hearing chain
how this case has moved, and where it goes next5 conditions of approval
Sample condition, 1 of 5: Setback increased from 220 to 300 feet from project perimeter for substations
The other 4 conditions of approval, verbatim, plus the amendments that changed the deal, are in the Project Report.
Follow this project, free
We'll email you the staff recommendation, the vote, and every condition the morning after each hearing. No card.
We'll email you a 6-digit code, no password.
Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.
Learn about Meeting Q&AMore projects in Hanover County
- Fast Mart · Approved
- Case SE 2026-000023 · Approved
- AR6 for family division off Bethany Church Road · Approved
- Case SC 2026-00021 · Approved
- Case SE 2025-00033 · Approved