Project · Santa Cruz County, AZ · Updated today

Hermosa Project (South32) - mine and Centro operating center

Patagonia Mountains / Harshaw Road area, near Patagonia; Centro in NogalesSouth32Under ReviewIndustrial

Tracking this deal? Follow it free, we'll email you when there's a decision

Sourced from Santa Cruz County meeting, Apr 1, 2026. ZoneWire tracks 28 projects in Santa Cruz County, AZ, updated within 24h of every meeting.

Where this stands

Zinc (and possible future manganese) mine on ~200 acres of private land; construction ~55% complete; two shafts ~50-65% complete; first underground zinc mining targeted mid-2026; zinc processing facility, tailings filtration plant (90% water reduction), fully enclosed material handling. Federal-land components: 138-kV UniSource power line, Flux Canyon access road, second tailings facility, drill pads. Centro remote operating center in Nogales for up to 200 workers, on track to open next year. Workforce to ramp to 600 employees in ~18 months, goal of 80% local Santa Cruz County residents. Final EIS and draft ROD issued March; objection period to April 20; final ROD early July; notice to proceed early September.

Case factsSource: ZoneWire
Project
Hermosa Project (South32) - mine and Centro operating center
Asset class
Industrial
Developer
South32
Location
Patagonia Mountains / Harshaw Road area, near Patagonia; Centro in Nogales
Scale
200 acres
County
Santa Cruz County, AZ
Jurisdiction
Santa Cruz County
Current status
Under Review

Follow this project, free

We'll email you the staff recommendation, the vote, and every condition the morning after each hearing. No card.

We'll email you a 6-digit code, no password.

or

Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.

Learn about Meeting Q&A

Related

Topics
IndustrialUnder ReviewPatagonia Mountains / Harshaw Road area, near Patagonia; Centro in NogalesSanta Cruz County, AZ

Hermosa Project (South32) - mine and Centro operating center

Under Review

Unlock the full hearing timeline, conditions, zoning detail, and contacts for this project, and every project in this market.

Track this with Pro