Skip to content

Project · Tulsa, OK · Updated today

Meta Data Center Expansion (Project Anthem Phase 2)

Fair Oaks area, East TulsaMeta / Robson family (developer)Under ReviewIndustrial
Follow this project

Tracking this deal? Follow it free, we'll email you when there's a decision

Sourced from Tulsa meeting, Feb 11, 2026. ZoneWire tracks 210 projects in Tulsa, OK, updated within 24h of every meeting.

Where this stands

Meta seeking to rezone additional 375 acres from agriculture to light industry for second data center campus. Original data center projected to use up to 1 billion gallons of water when fully operational.

Case factsSource: ZoneWire
Project
Meta Data Center Expansion (Project Anthem Phase 2)
Asset class
Industrial
Developer
Meta / Robson family (developer)
Location
Fair Oaks area, East Tulsa
Scale
375 acres
County
Tulsa, OK
Jurisdiction
Tulsa
Current status
Under Review

Follow this project, free

We'll email you the staff recommendation, the vote, and every condition the morning after each hearing. No card.

or

Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.

Learn about Meeting Q&A

Related

Topics
IndustrialUnder ReviewFair Oaks area, East TulsaTulsa, OK

Meta Data Center Expansion (Project Anthem Phase 2)

under_review