Where this stands
Rezoned PDR-2 to P
- Board of Supervisors approved it 11-0 on Jan 13, 2026.
- Project
- Street vacation
- Asset class
- Institutional
- Developer
- San Francisco Fire Department
- Location
- 1236 Carroll Avenue, Bayview
- County
- San Francisco, CA
- Jurisdiction
- San Francisco
- Latest action
- Rezoned PDR-2 → P
- Current status
- Approved
The hearing chain
how this case has moved, and where it goes next2 conditions of approval
All 2 conditions of approval, verbatim, plus the amendments that changed the deal, are in the Project Report.
The whole board record on this parcel, in one report.
Everything on this project, assembled: every decision and its full hearing chain, every condition, and the source links. One project, one price, however many hearings.
- Where it stands today, with the source meeting linked
- The full hearing chain, every hearing
- All 2 conditions of approval, verbatim
- The applicant's filings and representative
2 hearings, the 2 conditions verbatim, and the vote where one was recorded. More decisions attach to this project as they are heard, at no extra cost.
A manual parcel zoning report from Gridics starts at $999. This is not that report and does not replace it: it is the board record on this parcel, for $19.
Follow this project, free
We'll email you the staff recommendation, the vote, and every condition the morning after each hearing. No card.
We'll email you a 6-digit code, no password.
Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.
Learn about Meeting Q&AMore projects in San Francisco
- Potrero Power Station Special Use District planning code and zoning · Approved
- Amended development agreement for Potrero Power Station project · Approved
- Potrero Power Station Special Use District height and zoning · Awaiting final vote
- Potrero Power Station (Sep 28, 2026) · Awaiting final vote
- authorization for Glide Foundation · Awaiting final vote