Skip to content

Project · 1 decision so far · Tucson, AZ · Updated today

Large-scale data center UDC

ApprovedData Center

Tracking this deal? Follow it free, we'll email you when there's a decision

Sourced from Tucson meeting, Aug 5, 2026. ZoneWire tracks 134 projects in Tucson, AZ, updated within 24h of every meeting.

Where this stands

Large-scale data center UDC amendment (C8-25-04)

  • Tucson Mayor and City Council Meetings approved it 6-1 on Aug 5, 2026.
Case factsSource: ZoneWire
Project
Large-scale data center UDC
Asset class
Data Center
County
Tucson, AZ
Jurisdiction
Tucson
Latest action
Large-scale data center UDC amendment (C8-25-04)
Current status
Approved

The hearing chain

how this case has moved, and where it goes next
  1. Aug 5, 2026 · Tucson Mayor and City Council Meetings · Approved

3 conditions of approval

Sample condition, 1 of 3: return to Mayor and Council within one year for review of ordinance and implementation

General 3

The other 2 conditions of approval, verbatim, plus the amendments that changed the deal, are in the Project Report.

Follow this project, free

We'll email you the staff recommendation, the vote, and every condition the morning after each hearing. No card.

We'll email you a 6-digit code, no password.

or

Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.

Learn about Meeting Q&A

More projects in Tucson

Related

Topics
Data CenterApprovedTucson, AZ