Where this stands

Large-scale data center UDC amendment (C8-25-04)

  • The Tucson votes on Large-scale data center UDC by a 6-1 vote.
Case factsSource: ZoneWire
Project
Large-scale data center UDC
Asset class
Data Center
County
Tucson, AZ
Jurisdiction
Tucson
Latest action
Large-scale data center UDC amendment (C8-25-04)
Current status
Decided

The hearing chain

how this case has moved, and where it goes next
  1. Aug 5, 2026 · Tucson Mayor and City Council Meetings · Approved

3 conditions of approval

Sample condition, 1 of 3: return to Mayor and Council within one year for review of ordinance and implementation

Other 3

The other 2 conditions of approval, verbatim, plus the amendments that changed the deal, are in the Project Report.

Follow this project, free

We'll email you the staff recommendation, the vote, and every condition the morning after each hearing. No card.

We'll email you an activation link — one click, no password, unsubscribe anytime.

or

Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.

Learn about Meeting Q&A

Related

Topics
Data CenterDecidedTucson, AZ