Planning Commission Meeting, September 16, 2026

Recommends approval: Special Use Permit for Crossroads Technology Campus data center, 4-2

4h 10m35,469 words
249 mentionsmotion to approvecommercialpublic hearingcomprehensive planrezoningsubdivisionspecial use permitconditional useresidentialzoningland usedensityrezoneindustrialmixed usesetbackhistoric preservationapproveddeniedtraffic studydeferredSpotsylvania County, VA
Just researching this meeting? Get free Spotsylvania County alerts

What happened

On September 16, 2026, the Planning Commission recommended approval of Special Use Permit for Crossroads Technology Campus data center (4-2).

The Spotsylvania County Planning Commission recommended approval of SUP 26-0003, the Crossroads Technology Campus data center (up to 2,087,000 sq ft, 7 buildings, 3 substations, Amazon as user, developed by Kettler) on a 4-2 vote, with 54 staff conditions plus additional stipulat…

Meeting key facts
Jurisdiction
Spotsylvania County, VA
Governing body
Advisory (makes a recommendation)
Date
September 16, 2026
Decisions
4 zoning decisions
Outcome
Recommends approval, 4-2
Next step
Final board vote (pending)

Projects in this meeting (2)

SUP 26-0005

Recommended
3 conditions of approval

Crossroads Technology Campus Data Center

Recommended 4-2
38 conditions of approval

Free sample: decision 1 of 4

Special Use Permit for Tabernacle Church All Things Academy enrollment expansion

SUP 26-0005 to allow enrollment expansion of an existing private school operating under conditional use permit CP 94-08 from 60 to 100 children on approximately 3.29 acre parcels zoned Residential 1 at 7301 Old Plank Road in the Chancellor District. Recommended to Board of Supervisors. Vote unanimous (Wood, Fregoso, Grinnell, Phelps, Bell, Bullock all aye).

  • normal hours of operation limited to Monday through Friday 6 a.m. to 7 p.m.
  • maximum enrollment shall be 100 with at least one adult present for each 15 children
  • within 60 days of approval owner/applicant will apply for an educational occupancy building permit for maximum of 100 students

The other decisions are listed below. Available full write-ups and conditions are included with Pro.

Spotsylvania County access in Pro, $39/month.

Key Decisions (4)

Approved

Special Use Permit for Tabernacle Church All Things Academy enrollment expansion

Vote: unanimous3 conditions attachedMoved by Bell
Approved

15.2-2232 consistency review for Crossroads Technology Campus substations

Vote: 4-2
Approved

Special Use Permit for Crossroads Technology Campus data center

Vote: 4-238 conditions attached
Other

Parking ordinance review request (County Code 23-6.28.6)

Full write-ups and conditions for all 4 decisions in Pro.

Development Activity (4)

Tabernacle Church All Things Academy private school enrollment expansion

Other

Crossroads Technology Campus

Industrial

Harefield property residential/commercial development

Mixed-Use

Thornburg Commons

Residential

Market Signals (5)

Commercial Demand

Strong ongoing data center demand in Spotsylvania County, with roughly…

Infrastructure

A $480 million reuse-water (purple pipe) system serving four wastewater…

Infrastructure

Transmission-line routing to serve Crossroads' three substations (~894 MW) remains…

2 additional market signals with full detail in Pro.

Who spoke

20 distinct speakers; 5 identified names.

All speaker roles: 7 Public, 2 Staff, 1 Witness, 4 Commissioner, 1 Attorney, 2 Chair, 1 Applicant, 1 Applicant Rep, 1 Clerk.

Identified name roles: 1 Witness, 3 Commissioner, 1 Applicant Rep.

Speaker sample: Charlie Payne, Applicant Rep.

4 more identified names in Pro: 1 Witness, 3 Commissioner.

Full speaker roster in Pro

Meeting audio

Listen to the recording and select a timestamp with Pro.

Audio in Pro

Zoning terms (21)

249 recorded timestamps

  • motion to approve (3 timestamps)
  • commercial (12 timestamps)
  • public hearing (20 timestamps)
  • comprehensive plan (26 timestamps)
  • rezoning (3 timestamps)
  • subdivision (10 timestamps)

Decision moments (4)

Ask this meeting anything

The transcript is ready. Ask questions with answers cited to this meeting in Pro.

Meeting Q&A in Pro

Questions you can ask

  • What conditions were attached to the decisions?
  • What were the recorded votes?
  • Who spoke, and what did they discuss?

Go deeper on this meeting

4 recorded decisions, 41 conditions across 2 decisions. Available full write-ups are included with Pro for Spotsylvania County.

Full write-up and conditions in Pro

Follow Spotsylvania County

Get the agenda when a meeting is posted, plus decision and analysis alerts.

We'll email you a 6-digit code, no password.

or