Planning Commission, June 10, 2026

Recommends approval: Comprehensive plan amendment for high-voltage transmission line corridors, 6-0

1h 47m15,620 words
105 mentionssetbackcomprehensive planconditional usezoningcommercialmixed useresidentialindustrialland useapprovedpublic hearingplatmotion to approvedensityStafford County, VA
Just researching this meeting? Get free Stafford County alerts

What happened

On June 10, 2026, the Planning Commission recommended approval of Comprehensive plan amendment for high-voltage transmission line corridors (6-0).

The Stafford County Planning Commission approved three land-use items unanimously (6-0). It approved CUP 25156691 for an eight-foot fence height exception in the B2 district on tax map parcel 37-25 along Center Point Parkway to screen an approved data center campus (Pemberton/Cen…

Meeting key facts
Jurisdiction
Stafford County, VA
Governing body
Advisory (makes a recommendation)
Date
June 10, 2026
Decisions
5 zoning decisions
Outcome
Recommends approval, 6-0
Next step
Final board vote (pending)

Projects in this meeting (4)

Wyatt Lane Solar

Recommended 6-0

High-Voltage Transmission Line Corridors

Recommended

Wyatt Lane Solar facility

Recommended 6-0
11 conditions of approval

Initiate

Recommended 6-0

Free sample: decision 1 of 5

Fence height exception CUP at Center Point Parkway

Conditional use permit for an eight-foot fence within the B2 Urban Commercial Zoning District on tax map parcel 37-25, a 44.6-acre property in the Hartwood Election District along Center Point Parkway. Purpose is to screen and secure an approved data center campus (Centerport Gateway/Pemberton Tech Center). Applicant represented by Jessica Pfeiffer with Walsh Colucci; operator team includes Worldwide Mission Critical. Passed 6-0.

  • Exception to Stafford County Code Section 28-38D in the B2 district
  • fencing system in substantial conformance with the GDP
  • site fencing maintained at all times
  • material change from GDP requires revised site plan review and approval prior to installation
  • CUP may be revoked for violations

The other decisions are listed below. Available full write-ups and conditions are included with Pro.

Stafford County access in Pro, $39/month.

Key Decisions (5)

Approved

Fence height exception CUP at Center Point Parkway

Vote: 6-05 conditions attachedMoved by Shelton
Approved

Comprehensive plan compliance review for Wyatt Lane Solar

Vote: 6-0Moved by Shelton
Approved

Conditional use permit for Wyatt Lane Solar facility

Vote: 6-011 conditions attachedMoved by Shelton
Approved

Comprehensive plan amendment for high-voltage transmission line corridors

Vote: 6-0Moved by Shelton
Approved

Initiate public hearing on drive-thru ordinance amendment

Vote: 6-0Moved by Siegman

Full write-ups and conditions for all 5 decisions in Pro.

Development Activity (3)

Centerport Gateway Pemberton Tech Center data center campus

Industrial

Wyatt Lane Solar

Other

Stafford County Fire and Rescue Station No. 9

Infrastructure

Market Signals (4)

Infrastructure

Data center development is driving major utility infrastructure demand in…

Infrastructure

The county is proactively amending its comprehensive plan to push…

Commercial Demand

A proposed ordinance amendment easing drive-thru CUP requirements and reducing…

Sentiment

Community sentiment favors solar development as low-impact, tax-positive land use,…

Who spoke

18 distinct speakers; 10 identified names.

All speaker roles: 5 Commissioner, 6 Public, 1 Chair, 3 Staff, 1 Applicant, 1 Attorney, 1 Applicant Rep.

Identified name roles: 4 Commissioner, 3 Staff, 1 Applicant, 1 Attorney, 1 Applicant Rep.

Speaker sample: Tyler McGilvery, Applicant.

9 more identified names in Pro: 4 Commissioner, 3 Staff, 1 Attorney, 1 Applicant Rep.

Full speaker roster in Pro

Meeting audio

Listen to the recording and select a timestamp with Pro.

Audio in Pro

Zoning terms (14)

105 recorded timestamps

  • setback (9 timestamps)
  • comprehensive plan (24 timestamps)
  • conditional use (8 timestamps)
  • zoning (6 timestamps)
  • commercial (4 timestamps)
  • mixed use (1 timestamps)

Decision moments (5)

Ask this meeting anything

The transcript is ready. Ask questions with answers cited to this meeting in Pro.

Meeting Q&A in Pro

Questions you can ask

  • What conditions were attached to the decisions?
  • What were the recorded votes?
  • Who spoke, and what did they discuss?

Go deeper on this meeting

5 recorded decisions, 16 conditions across 2 decisions. Available full write-ups are included with Pro for Stafford County.

Full write-up and conditions in Pro

Follow Stafford County