Skip to content
Stafford County Meetings

Planning Commission, June 24, 2026

Recommends approval: Rezoning at 1001 Richmond Highway (Stafford One Industrial), 4-0

1h 14m10,327 words
79 mentionszoningrezoningindustrialpublic hearingcomprehensive planland usedensitymixed usesetbackcommercialresidentialplatdeferredmotion to approveStafford County, VA
Just researching this meeting? Get free Stafford County alerts

What happened

On June 24, 2026, the Planning Commission recommended approval of Rezoning at 1001 Richmond Highway (Stafford One Industrial) (4-0).

Stafford County Planning Commission recommended approval (4-0, three absent) of the Stafford One Industrial rezoning of a 38.6-acre parcel at 1001 Richmond Highway from A-1 agricultural to M-2 heavy industrial with proffers, for a ~30,000 sq ft warehouse (case RC23155322, Ordinan…

Meeting key facts
Jurisdiction
Stafford County, VA
Governing body
Advisory (makes a recommendation)
Date
June 24, 2026
Decisions
3 zoning decisions
Outcome
Recommends approval, 4-0
Next step
Final board vote (pending)

Projects in this meeting (2)

1001 Richmond Highway

Recommended 4-0
1001 Richmond Highway, Falmouth District · Stafford One Investment LLC
7 conditions of approval

Stafford One Industrial (parcel 46.1) from A-1 to M-2 [case: 801 Teleg

Recommended 5-2
801 Telegraph Road, Griffis-Widewater District · Carlos Castro
13 conditions of approval

Free sample: decision 1 of 3

Rezoning at 1001 Richmond Highway (Stafford One Industrial)

Recommended approval of rezoning Tax Map Parcel 46-1, 38.6 acres, from A-1 agricultural to M-2 heavy industrial with proffers, to allow ~30,000 sq ft industrial warehouse. Applicant Stafford One Investment LLC (Mr. John), agent Charlie Payne of Hirschler. Data center use prohibited via proffers. Trip cap 999 vehicles/day. Vote 4-0 with three absent (Codell, Hamlin, Siegmund).

  • Development in conformance with GDP
  • prohibited uses including data centers
  • heat-reducing roofing material
  • Phase 1/2/3 archaeological studies as needed
  • second entrance required if footprint exceeds 30,000 sq ft
  • max 999 vehicle trips per day
  • tree preservation area to remain undisturbed except for safety, utilities, stormwater or public facilities

The other decisions are listed below. Available full write-ups and conditions are included with Pro.

Get every Stafford County meeting with full decisions, votes, and zoning details, within hours of each session.

Stafford County access in Pro, $39/month.

Key Decisions (3)

Approved

Rezoning at 1001 Richmond Highway (Stafford One Industrial)

Vote: 4-07 conditions attached
Approved

Rezoning at 801 Telegraph Road

Vote: 4-05 conditions attached
Approved

Five time-extension requests

Vote: 4-0Moved by Shelton

Full write-ups and conditions for all 3 decisions in Pro.

Zoning Changes (2)

A-1M-238.6 acres
R-1B-10.41 acre

Development Activity (2)

Stafford One Industrial

Industrial

801 Telegraph Road general office

Commercial

Market Signals (4)

Commercial Demand

A previously planned data center option on the Stafford One…

Infrastructure

Fire marshal code requiring a second access point above 30,000…

Sentiment

Board of Supervisors expressed uncertainty over how to evaluate data…

Housing Demand

A public speaker cited a 2024 median home value announced…

Agenda results

DEFERRED - DATE TBD -- PLANNING AND ZONING plan amendment

No vote recorded

DEFERRED - DATE TBD -- PLANNING AND ZONING plan amendment

No vote recorded

COMPREHENSIVE PLAN 5-YEAR UPDATE SUBCOMMITTEE NEXT MEETING - THURSDAY, JUNE 25, 2026 @… plan amendment

No vote recorded

DEFERRED - DATE TBD -- PLANNING AND ZONING conditional use permit

No vote recorded

Who spoke

16 distinct speakers; 7 identified names.

All speaker roles: 3 Commissioner, 4 Staff, 2 Applicant Rep, 4 Public, 1 Witness, 1 Chair, 1 Attorney.

Identified name roles: 3 Staff, 1 Commissioner, 2 Applicant Rep, 1 Witness.

Speaker sample: Marcelo Pozo, Applicant Rep.

6 more identified names in Pro: 3 Staff, 1 Commissioner, 1 Applicant Rep, 1 Witness.

Full speaker roster in Pro

Meeting audio

Listen to the recording and select a timestamp with Pro.

Audio in Pro

Zoning terms (14)

79 recorded timestamps

  • zoning (12 timestamps)
  • rezoning (6 timestamps)
  • industrial (16 timestamps)
  • public hearing (6 timestamps)
  • comprehensive plan (12 timestamps)
  • land use (6 timestamps)

Decision moments (3)

Ask this meeting anything

The transcript is ready. Ask questions with answers cited to this meeting in Pro.

Meeting Q&A in Pro

Questions you can ask

  • What conditions were attached to the decisions?
  • What were the recorded votes?
  • Who spoke, and what did they discuss?

Go deeper on this meeting

3 recorded decisions, 12 conditions across 2 decisions. Available full write-ups are included with Pro for Stafford County.

Full write-up and conditions in Pro

Follow Stafford County

Get the agenda when a meeting is posted, plus decision and analysis alerts.

We'll email you a 6-digit code, no password.

or