August 26, 2026 Planning Commission Meeting, August 26, 2026

Approves Accokeek Center Zoning Reclassification (A-1/A-2/B-3 to M-2) for data center campus, 4-3

7h 24m63,714 words
419 mentionszoningpublic hearingapprovedconditional useland usecomprehensive planrezoneresidentialindustrialrezoningcommercialsetbackmixed useoverlay districtdeferredsubdivisionvariancemotion to approvedensitytraffic studyplatStafford County, VA
View agenda
Just researching this meeting? Get free Stafford County alerts

What happened

The Stafford County Planning Commission recommended approval of the Accokeek Center project — a rezoning of approximately 120.88 acres at the west side of Richmond Highway (~2,500 feet north of Eskimo Hill Road) from A-1, A-2, and B-3 to M-2 with proffers, plus a comprehensive pl…

Meeting key facts
Jurisdiction
Stafford County, VA
Governing body
Final authority
Date
August 26, 2026
Decisions
6 zoning decisions
Outcome
Approved, 4-3

Projects in this meeting (6)

Sheetz

Recommended 6-1
West side of Cambridge Street (US Route 1) between Enon Road and Porter Lane, Falmouth District · Sheetz
11 conditions of approval
Open this projectProject Report, $19 · or in Pro

Accokeek Center Zoning Reclassification (A-1/A-2/B-3 to M-2) for data

Recommended 4-3
West side of Richmond Highway, approximately 2,500 feet north of Eskimo Hill Road, Falmouth District · Falmouth Tech LLC
25 conditions of approval
Open this projectProject Report, $19 · or in Pro

Accokeek Center

Recommended 4-3
11 conditions of approval

Comprehensive Plan Five-Year Update

Awaiting final vote

Accokeek Center

Recommended 4-3

Sheetz

Recommended 6-1
4 conditions of approval

Free sample: decision 1 of 6

Accokeek Center Zoning Reclassification (A-1/A-2/B-3 to M-2) for data center campus

Rezoning of approximately 120.88 acres on the west side of Richmond Highway (~2,500 feet north of Eskimo Hill Road) from A-1 Agricultural, A-2 Rural Residential, and B-3 Office to M-2 Heavy Industrial with proffers, to permit a data center campus with two buildings totaling 590,000 sq ft (down from three buildings/690,000 sq ft in April) and an electric substation. Applicant Falmouth Tech LLC, represented by Charlie Payne with Hirschler. Anticipated power demand 122 MW; ~$13.5M annual tax revenue at buildout. Modified setbacks requested (750 ft reduced to 550/399 ft in some locations; buffers reduced to 60 ft along I-95 and ~40-47 ft at emergency access). Motion by Commissioner Oates, seconded by Commissioner Bratton. Passed 4-3 (Cottle and Barnes among those opposed).

  • Property developed in general conformance with GDP
  • limit development to data center and accessory uses only
  • max 590,000 sq ft and 65-foot building height
  • minimum 40% open space
  • reduced vegetative buffers as depicted on GDP
  • tree preservation areas with 1.5x replanting requirement
  • prohibit use of groundwater for data center operations
  • require reuse water as sole primary cooling water source
  • prohibit public or private potable water for industrial cooling
  • provide written verification from electric utility regarding timing of power
  • sound attenuation and mechanical screening per GDP
  • Tier 4 generator standards
  • AED in each building
  • repair roadway damage from construction
  • approval of emergency action plan prior to first CO
  • max 443 vehicle trips per day
  • 10-foot shared use path along Richmond Highway
  • northbound left turn lane, southbound right turn, raised median
  • right-of-way dedication up to 80 feet from centerline
  • $50,000 transportation projects
  • $1.5M courthouse renovation
  • $1.25M technology infrastructure
  • $1.65M Belmont Ferry Farm bike trail
  • $1.5M new fire and rescue station
  • $500,000 Central Rappahannock Regional Library

The other decisions are listed below by title. The full write-up, verbatim conditions, and the audio at each vote are in Pro.

Meeting Summary

The Stafford County Planning Commission recommended approval of the Accokeek Center project — a rezoning of approximately 120.88 acres at the west side of Richmond Highway (~2,500 feet north of Eskimo Hill Road) from A-1, A-2, and B-3 to M-2 with proffers, plus a comprehensive pl…

Get email alerts for new Stafford County meetings

Key Decisions (6)

Approved

Accokeek Center Zoning Reclassification (A-1/A-2/B-3 to M-2) for data center campus

Vote: 4-3Conditions attached
Approved

Accokeek Center Comprehensive Plan Compliance Review for electric substation

Vote: 4-3
Approved

Accokeek Center Conditional Use Permit for electric substation

Vote: 4-3Conditions attached
Approved

Sheetz at Enon Road Zoning Reclassification (A-1/B-1 to B-2)

Vote: 6-1Conditions attached
Approved

Sheetz at Enon Road Conditional Use Permit

Vote: 6-1Conditions attached
Deferred

Comprehensive Plan Five-Year Update

Vote: unanimous

Zoning Changes (2)

A-1M-2120.88 acres
A-1B-23.88 acres

Development Activity (4)

Accokeek Center Data Center Campus

Industrial

Sheetz at Enon Road

Commercial

Old Potomac Church Data Center

Industrial

Stafford Technology Campus (STC)

Industrial

Market Signals (6)

Infrastructure

Dominion Energy's changed queuing process (batch submissions to the SCC…

Infrastructure

Stafford's reuse (purple pipe) water system, being built and financed…

Commercial Demand

Strong data center investment corridor forming along Route 1 in…

Who Spoke (38)

Staff · 3Applicant's RepPublic · 22

On the record: 3 staff members, the applicant's representative, and 22 members of the public.

Agenda scorecard

ZoneWire called 2 of 2 land-use forecasts on this agenda.

This season: 11 of 11 (100%) forecasts called in this county.

PLANNING AND ZONING conditional use permit

Approved 4-3ZoneWire called it
freeApproved 4-311 conditions of approval
11 conditions, the audio at the vote, and this case's history
See it in ProStart a free 7-day trial, then $39/mo

PLANNING AND ZONING conditional use permit

Approved 6-1ZoneWire called it
freeApproved 6-14 conditions of approval
4 conditions, the audio at the vote, and this case's history
See it in ProStart a free 7-day trial, then $39/mo

Meeting Intelligence Preview

Ask this meeting anything

Ask who voted, what conditions passed, and what staff recommended for "August 26, 2026 Planning Commission Meeting - 2026-08-26", with every answer cited to the transcript. Included with Pro.

Learn about Meeting Q&A

Get every Stafford County meeting with full decisions, votes, and zoning details, within hours of each session.

Just want to know when new Stafford County meetings are posted? Get free email alerts below.

Follow Stafford County

Get the agenda when a meeting is posted, plus decision and analysis alerts.

We'll email you a 6-digit code, no password.

or