August 26, 2026 Planning Commission Meeting, August 26, 2026
Approves Accokeek Center Zoning Reclassification (A-1/A-2/B-3 to M-2) for data center campus, 4-3
What happened
The Stafford County Planning Commission recommended approval of the Accokeek Center project — a rezoning of approximately 120.88 acres at the west side of Richmond Highway (~2,500 feet north of Eskimo Hill Road) from A-1, A-2, and B-3 to M-2 with proffers, plus a comprehensive pl…
- Jurisdiction
- Stafford County, VA
- Governing body
- Final authority
- Date
- August 26, 2026
- Decisions
- 6 zoning decisions
- Outcome
- Approved, 4-3
Projects in this meeting (6)
Each is its own project; some span multiple hearingsSheetz
Recommended 6-1Accokeek Center Zoning Reclassification (A-1/A-2/B-3 to M-2) for data
Recommended 4-3Accokeek Center
Recommended 4-3Comprehensive Plan Five-Year Update
Awaiting final voteAccokeek Center
Recommended 4-3Sheetz
Recommended 6-1Free sample: decision 1 of 6
Accokeek Center Zoning Reclassification (A-1/A-2/B-3 to M-2) for data center campus
Rezoning of approximately 120.88 acres on the west side of Richmond Highway (~2,500 feet north of Eskimo Hill Road) from A-1 Agricultural, A-2 Rural Residential, and B-3 Office to M-2 Heavy Industrial with proffers, to permit a data center campus with two buildings totaling 590,000 sq ft (down from three buildings/690,000 sq ft in April) and an electric substation. Applicant Falmouth Tech LLC, represented by Charlie Payne with Hirschler. Anticipated power demand 122 MW; ~$13.5M annual tax revenue at buildout. Modified setbacks requested (750 ft reduced to 550/399 ft in some locations; buffers reduced to 60 ft along I-95 and ~40-47 ft at emergency access). Motion by Commissioner Oates, seconded by Commissioner Bratton. Passed 4-3 (Cottle and Barnes among those opposed).
- Property developed in general conformance with GDP
- limit development to data center and accessory uses only
- max 590,000 sq ft and 65-foot building height
- minimum 40% open space
- reduced vegetative buffers as depicted on GDP
- tree preservation areas with 1.5x replanting requirement
- prohibit use of groundwater for data center operations
- require reuse water as sole primary cooling water source
- prohibit public or private potable water for industrial cooling
- provide written verification from electric utility regarding timing of power
- sound attenuation and mechanical screening per GDP
- Tier 4 generator standards
- AED in each building
- repair roadway damage from construction
- approval of emergency action plan prior to first CO
- max 443 vehicle trips per day
- 10-foot shared use path along Richmond Highway
- northbound left turn lane, southbound right turn, raised median
- right-of-way dedication up to 80 feet from centerline
- $50,000 transportation projects
- $1.5M courthouse renovation
- $1.25M technology infrastructure
- $1.65M Belmont Ferry Farm bike trail
- $1.5M new fire and rescue station
- $500,000 Central Rappahannock Regional Library
The other decisions are listed below by title. The full write-up, verbatim conditions, and the audio at each vote are in Pro.
Meeting Summary
The Stafford County Planning Commission recommended approval of the Accokeek Center project — a rezoning of approximately 120.88 acres at the west side of Richmond Highway (~2,500 feet north of Eskimo Hill Road) from A-1, A-2, and B-3 to M-2 with proffers, plus a comprehensive pl…
Key Decisions (6)
Accokeek Center Zoning Reclassification (A-1/A-2/B-3 to M-2) for data center campus
Accokeek Center Comprehensive Plan Compliance Review for electric substation
Accokeek Center Conditional Use Permit for electric substation
Sheetz at Enon Road Zoning Reclassification (A-1/B-1 to B-2)
Sheetz at Enon Road Conditional Use Permit
Comprehensive Plan Five-Year Update
Development Activity (4)
Accokeek Center Data Center Campus
Industrial
Sheetz at Enon Road
Commercial
Old Potomac Church Data Center
Industrial
Stafford Technology Campus (STC)
Industrial
Market Signals (6)
Infrastructure
Dominion Energy's changed queuing process (batch submissions to the SCC…
Infrastructure
Stafford's reuse (purple pipe) water system, being built and financed…
Commercial Demand
Strong data center investment corridor forming along Route 1 in…
Who Spoke (38)
On the record: 3 staff members, the applicant's representative, and 22 members of the public.
Agenda scorecard
Our pre-meeting forecast, graded against the recorded voteZoneWire called 2 of 2 land-use forecasts on this agenda.
This season: 11 of 11 (100%) forecasts called in this county.
PLANNING AND ZONING conditional use permit
PLANNING AND ZONING plan amendment
COMPREHENSIVE PLAN 5-YEAR UPDATE PLANNING DIRECTOR'S REPORT plan amendment
Meeting Intelligence Preview
Ask this meeting anything
Ask who voted, what conditions passed, and what staff recommended for "August 26, 2026 Planning Commission Meeting - 2026-08-26", with every answer cited to the transcript. Included with Pro.
Learn about Meeting Q&AGet every Stafford County meeting with full decisions, votes, and zoning details, within hours of each session.
7-day free trial. Cancel anytime.
Just want to know when new Stafford County meetings are posted? Get free email alerts below.
Follow Stafford County
Get the agenda when a meeting is posted, plus decision and analysis alerts.
We'll email you a 6-digit code, no password.