The Tulsa County Board of County Commissioners approved PUD 876 for warehouse, commercial, and wholesale uses on 16.5 acres at 9802 North Real Avenue in Sperry, with a unanimous vote following Planning Commission recommendation. The meeting also opened bids for the Garnett Road widening project with five contractors submitting proposals, and addressed multiple infrastructure projects including bridge repairs and road overlays.
Key Decisions (5)
PUD 876 Zoning Approval - Warehouse/Commercial Uses at 9802 North Real Avenue, Sperry
Approved new PUD 876 to allow warehouse, commercial, and wholesale uses on approximately 16.5 acres at 9802 North Real Avenue, Sperry. Current zoning is CS plus PUD. Planning Commission voted 10-0-0 to approve per staff recommendation. Found conforming to Highway 75 planning area of Tulsa County land use comprehensive plan. Applicant representative Robert Bell of 101 East Aquarium Place, Jinx.
Garnett Road Widening Project Bids Received
Opened bids for Garnett Road widening project from five contractors: BECO Contractors Incorporated, Cherokee Pride Construction Incorporated, Crossland Heavy Contractors, Grade Line Construction LLC, and Timber Wolf Excavating. Referred to procurement and engineers for review and recommendations.
Short Creek Reinforcement Installation Bids
Received bids for installation reinforcement Short Creek from Impact Contractors LLC and The Inspired Group LLC. Referred to procurement for review and recommendation.
Sheriff Food Services Bids Received
Opened bids for sheriff's food services from Aramark Food, Benchmark Government Solutions, mimeo.com, The Inspired Group LLC, and Trinity Services Group Incorporated. Referred to procurement for review and recommendation.
51st Street Project Pre-Bid Meeting Announced
Mandatory pre-bid meeting scheduled for 51st Street project from 177th to 193rd Street, including roundabout, at 1:00 PM in commission room.
Zoning Changes (1)
9802 North Real Avenue, Sperry
Robert Bell (representative)
Development Activity (1)
PUD 876 Warehouse/Commercial Development
16.5 acres for warehouse, commercial, and wholesale uses along Highway 75 corridor. Site has been cleared of vegetation.
Market Signals (3)
Infrastructure
Tulsa County collected over $1 billion in property taxes for the first time ever, running 0.7% ahead of prior year collection rates at 89.6%.
Commercial Demand
PUD 876 described as one of the first developments on the Highway 75 Corridor new master plan, indicating emerging commercial corridor development.
Infrastructure
Multiple road infrastructure projects underway including 111th, 121st, and 131st intersection overlays, Bridge 18 reopening on North Sheridan, and Garnett Road widening with five competitive bids received.