Project · 2 decisions so far · Monticello, MN · Updated today

Data center campus in Edmondson Business Center DCPUD

ContinuedData Center

Tracking this deal? Follow it free, we'll email you when there's a decision

Sourced from Monticello meeting, Oct 6, 2026. ZoneWire tracks 52 projects in Monticello, MN, updated within 24h of every meeting.

Where this stands

Conditional use permit for data center campus in Edmondson Business Center DCPUD

  • City Council continued it on Nov 9, 2026.
Case factsSource: ZoneWire
Project
Data center campus in Edmondson Business Center DCPUD
Asset class
Data Center
County
Monticello, MN
Jurisdiction
Monticello
Latest action
Conditional use permit for data center campus in Edmondson Business Center DCPUD
Current status
Continued

The hearing chain

how this case has moved, and where it goes next
  1. Oct 6, 2026 · Planning Commission · Recommended
  2. Nov 9, 2026 · City Council · Continued · pending

5 conditions of approval

Sample condition, 1 of 5: Exhibit Z conditions

General 5

The other 4 conditions of approval, verbatim, plus the amendments that changed the deal, are in the Project Report.

Follow this project, free

We'll email you the staff recommendation, the vote, and every condition the morning after each hearing, starting with the next pending vote. No card.

We'll email you a 6-digit code, no password.

or

Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.

Learn about Meeting Q&A

More projects in Monticello

Related

Topics
Data CenterContinuedMonticello, MN