Project · 1 decision so far · San Francisco, CA · Updated yesterday
949 Post Street
Tracking this deal? Follow it free, we'll email you when there's a decision
Sourced from San Francisco meeting, Feb 12, 2026. ZoneWire tracks 246 projects in San Francisco, CA, updated within 24h of every meeting.
Where this stands
Conditional use authorization modifying affordability terms at 949 Post Street
- Planning Commission approved it 7-0 on Feb 12, 2026.
- Project
- 949 Post Street
- Asset class
- Residential
- Developer
- John Warner ownership group
- County
- San Francisco, CA
- Jurisdiction
- San Francisco
- Latest action
- Conditional use authorization modifying affordability terms at 949 Post Street
- Current status
- Approved
The hearing chain
how this case has moved, and where it goes next2 conditions of approval
All 2 conditions of approval, verbatim, plus the amendments that changed the deal, are in the Project Report.
1 credit ($19), or Pro at $39/mo with 3 Project Reports included
The whole board record on this parcel, in one report.
Everything on this project, assembled: the decision in full, every condition, and the source links. One project, one price.
- Where it stands today, with the source meeting linked
- This hearing in full, with the vote and conditions
- All 2 conditions of approval, verbatim
- The applicant's filings and representative
1 credit ($19), or Pro at $39/mo with 3 Project Reports included
1 hearing, the 2 conditions verbatim, and the vote where one was recorded. More decisions attach to this project as they are heard, at no extra cost.
A manual parcel zoning report from Gridics starts at $999. This is not that report and does not replace it: it is the board record on this parcel, for $19.
Follow this project, free
We'll email you the staff recommendation, the vote, and every condition the morning after each hearing. No card.
We'll email you a 6-digit code, no password.
Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.
Learn about Meeting Q&AMore projects in San Francisco
- 36-38 Coff Street · Continued
- Extension of citywide interim zoning moratorium · Approved
- Landmark designation of Transamerica Pyramid referred back to committe · Continued
- Extension of citywide data center moratorium for 10 months and 15 days · Awaiting final vote
- Adoption of Planning Department 45-day data center moratorium report · Awaiting final vote