Case R26-133

ContinuedData Center

Tracking this deal? Follow it free, we'll email you when there's a decision

Sourced from Stafford County meeting, Jul 7, 2026. ZoneWire tracks 142 projects in Stafford County, VA, updated within 24h of every meeting.

Where this stands

CUP for data center building height and electrical substation (Potomac Creek Campus)

  • July 07, 2026 Board of Supervisors Meeting continued it on Jul 7, 2026.
Case factsSource: ZoneWire
Project
Case R26-133
Asset class
Data Center
County
Stafford County, VA
Jurisdiction
Stafford County
Latest action
CUP for data center building height and electrical substation (Potomac Creek Campus)
Current status
Continued

The hearing chain

how this case has moved, and where it goes next
  1. Jul 7, 2026 · July 07, 2026 Board of Supervisors Meeting · Continued · pending

1 condition of approval

General 1

The condition of approval, verbatim, plus the amendments that changed the deal, are in the Project Report.

Follow this project, free

We'll email you the staff recommendation, the vote, and every condition the morning after each hearing, starting with the next pending vote. No card.

We'll email you a 6-digit code, no password.

or

Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.

Learn about Meeting Q&A

More projects in Stafford County

Related

Topics
Data CenterContinuedStafford County, VA