Project · Mount Pleasant, WI · Updated today
Microsoft Area 2 data center campus
Tracking this deal? Follow it free, we'll email you when there's a decision
Sourced from Mount Pleasant meeting, Oct 14, 2026. ZoneWire tracks 29 projects in Mount Pleasant, WI, updated within 24h of every meeting.
Where this stands
Seven one-story data center buildings (A-G), office, storage, two substations, and a guardhouse. About 600,000 sq ft more than the prior plan. Roughly 10-year build-out, starting with the northeast buildings. Sound walls of 25-30 ft on other sites. Site is more than one square mile.
- Project
- Microsoft Area 2 data center campus
- Asset class
- Industrial
- Developer
- Microsoft
- Location
- 12023 Durand Avenue
- Scale
- 600,000 sq ft
- County
- Mount Pleasant, WI
- Jurisdiction
- Mount Pleasant
- Current status
- Approved
Follow this project, free
We'll email you the staff recommendation, the vote, and every condition the morning after each hearing. No card.
We'll email you a 6-digit code, no password.
Ask AI about this project. Cited answers on the vote, conditions, and what each speaker argued.
Learn about Meeting Q&AMore projects in Mount Pleasant
- Fiona Fields revised · Awaiting final vote
- Microsoft Area 2 data center master · Awaiting final vote
- Sidewalk exception for Villas · Awaiting final vote
- Loading Dock Additions · Awaiting final vote
- 26-02 - Emerson Road · Voted
Related
Microsoft Area 2 data center campus
ApprovedUnlock the full hearing timeline, conditions, zoning detail, and contacts for this project, and every project in this market.
Track this with Pro